A) A,C,D,E
B) A,B,D,E
C) A,C,B,D,E
D) A,D,E
E) None of these
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Activities
B) Cost
C) Profit
D) Time
E) Milestones
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Total time is 13 days,total cost is $1500
B) Total time is 12 days,total cost is $2000
C) Total time is 12 days,total cost is $2300
D) Total time is 11 days,total cost is $1850
E) Total time is 11 days,total cost is $2350
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Pure Project
B) Task force
C) Matrix Project
D) Functional Project
E) PERT
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The Late Finish is 12
B) The Early Finish is 10
C) The slack for this activity is 2
D) The duration of this activity is 2
E) The activity is on the critical path
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days
Correct Answer
verified
Multiple Choice
A) Extra Value Materials-premium quality raw materials at the project site.
B) Enterprise Vacation Matrix-A chart indicating team members planned vacation absences
C) Earned Value Management-a technique for measuring project progress objectively.
D) Early Vision Management-An technique used in early project planning meetings for activities that set expectations to highlight and avoid "scope creep."
E) External Variance Measurement-identifying the degree to which project time and cost variances were due to forces and issues uncontrollable by the project manager.
Correct Answer
verified
Multiple Choice
A) Gantt Chart
B) PERT Chart
C) Bar/Milestone Chart
D) Total Program Cost Breakdown
E) EVM Chart
Correct Answer
verified
Multiple Choice
A) Team members can work on several projects
B) Functional area is a "home" after the project is completed
C) There are duplicated resources
D) Lines of communication are shortened
E) Overall organizational policies and goals can be ignored
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 72
Related Exams